conduct a compliance monitoring inspection. It was fine at the
time of the inspection with 6.5 mm of rain falling over the previous 48 hours.
Monk Rd Site:
The discharged wood waste appeared to be very clean and free of unacceptable wastes.
The new pond pipe had been connected to the existing pipe that led down to the
culvert under Monk Rd. Due to low flow conditions the culvert at Monk Road was only
discharging undiluted contaminated spring water (i.e. no freshwater flow was
occurring from
the Taranaki Regional Council
between 26 May 2022 and 06 July 2022
consideration of matters such as those expressed in the
NPS-FM objective. Given that the Council can only
consider policies that relate to the matters over which
the Council has reserved control through the plan itself,
the Council is unable to take into account matters that
fall outside this scope.
You will be aware that, with few exceptions (such as
this resource consent
Act). Rules 35 and 36 of the RFWP do not
include any matters of control that expressly allow for the consideration of matters such as those expressed in
the NPS-FM objective. Given that the Council can only consider policies that relate to the matters over which
the Council has reserved control through the plan itself, the Council is unable to take into account matters
that fall outside this scope.
In terms of the notification assessment and when deciding whether a person is an affected
propagation and consequent
dissemination of the endangered
rhododendrons whose future the
Pukeiti Rhododendron Trust is trying
to secure. Members got an opportunity
to see the Rouse House propagator and
improvements to the shade house
which have been paid for by The Trust.
These improvements are designed to
increase the success rate of the
propagation efforts.
The Soup and Large Leaf
Rhododendron Day was once again
threatened by rain but it was decided
to go ahead with it anyway. As it
page
9
3.2 Results
3.2.1 Inspections
08 December 2020
An inspection was undertaken to assess compliance with the wastewater discharge consent. A prolonged
period of rain occurred prior to the inspection. The yard was relatively clean and tidy. No evidence of spills.
The discharge of stormwater onsite into the roadside drain looked much improved from the last inspection.
A sample of the settling pond discharge into the wetland was unable to be collected due to a new
Ratapiko from the Manganui River through the Motukawa Race.
To allow the diversion of water from the Manganui River, a concrete weir was constructed across
the Manganui River downstream from Tariki Road. The weir is approximately 4 m high and was
constructed in 1927 (C. England pers. comm). The current consented take from the Manganui River
at the weir is 5.2 m3/s, with residual flows at the weir of 0.4 m3/s. However, when flow in the
Waitara River (at Bertrand Road gauge) falls below 5 m3/s, all of
landfill at Victoria Rd
Figure 2 Stratford landfill (shaded in yellow) and sampling locations
2.1 Inspections
27 August 2012
A site visit was made to conduct a compliance monitoring inspection and to take
groundwater samples. The weather was fine with 12 mm rain over the previous 24
hours.
Large areas of the crown of cap had been sown with grass. The re-grassed area had
been fenced off from stock. There were some areas of ponding around the stock
troughs and on the
in the skimmer pit under hot, sunny and
dry conditions, rather than any chemical source. The water level in the pit was very
low at the time of inspection. It was considered by Council officers that should
enough rain fall to cause a discharge, the pH would fall to well within consent limits
prior to any discharge occurring. No remedial action was required by the Council.
Also on 14 November 2012, a sample taken from the skimmer pit showed an elevated
suspended solids concentration. It