2021 to June 2022 by the Taranaki Regional Council (the Council)
concerning the monitoring programme for three resource consents held by Colin Boyd (the consent holder)
and his subsidiary Company, Surrey Road Landfarms Limited. The consent holder in conjunction with Mi
SWACO (the Company) controls and operates a drilling waste stockpile facility (Surrey Road stockpiling
facility), and a landfarming and landspreading operation located on Surrey Road, Tariki in the Waitara
catchment.
The
prepared a Traffic Impact
Report for both Junction and Oropuriri Structure Plan Development Areas.
Appendix 15: Junction Traffic Report and Appendix 16: Area N
Traffic Report were both prepared in 2018 in relation to concerns
expressed through landowner engagement around roading layout,
intersection locations and safety concerns. This report was used to finalise
roading layout shown on the Structure Plan maps.
In preparing this report we rely on the expert advice of Ms Alice West of
be proven).
Details of incidents, investigations and interventions are provided under each Company’s section of this
report.
page
7
2 Downer NZ Ltd
Introduction
Process description
The purpose of the Downer EDI Works Ltd (Downer) plant is to produce asphalt for use on roads and
driveways etc. A permanent drum mix plant has replaced the batch plant and mobile plant that were
formerly in use at the site.
The asphalt production is achieved by the following
Correction to minutes Tahora Saddle is on State Highway 43.
2.2 Concerns were raised around the detours on local roads when the Highway is
closed for works. It was noted that although the Councils approve these they do
have concerns around the width of the roads and the volume of traffic that use
these detours.
Taranaki Regional Transport Committee Meeting - Confirmation of Minutes - 1 September 2021
5
page
3. Development of Active Modes (Walking and Cycling)
3.1
power station located on Normanby Road
at Okaiawa, in the Waingongoro catchment. Utilising an existing weir across the Waingongoro River and
tunnel under Normanby Road, water is diverted for electricity generation. The station is located
approximately 3.2 km downstream of the weir, but due to the tight meander, these structures are located
only 90 m apart. This report for the period July 2021 to June 2022 describes the monitoring programme
implemented by the Taranaki Regional Council (the
Greymouth Petroleum Mining Group Ltd Turangi A Well Hydraulic Fracturing Report 2018-2021
activities 21
Appendix B — Total RLTP Expenditure in Taranaki by Activity Class for
2019/20 .......................................................................................................... 23
Appendix C — Community Road Safety Programme report for 2019/20
(High then Medium Activities) .............................................................. 24
Key acronyms used
AC Activity Class
AO Approved Organisation
BC Business Case
LTMA Land …
and extrusion plant situated at Paraite Road, in the
Mangaone and Mangati catchments, Bell Block. The location of the site is shown in Figures 1 and 2.
Copper and brass foundries and extrusion processes had previously been operated at the site. Copper
processing ceased in June 2002 and brass processing ceased in January 2003. MASL also previously
operated a separate powdercoating facility on Connett Road in the Mangati catchment. This operation was
shifted to the main Paraite Road site
page
Executive summary
The Stratford District Council (SDC) operates a municipal wastewater treatment plant (WWTP) located on
Victoria Road at Stratford, in the Patea catchment. This report for the period July 2021 to June 2022
describes the monitoring programme implemented by the Taranaki Regional Council (the Council) to assess
SDC’s environmental and consent compliance performance during the period under review. The report also
details the results of the monitoring