The new East Stand

The old TSB Stand was originally scheduled to be repaired but this wasn’t possible because of poor ground conditions. Instead it was demolished and a new flexible, scalable East Stand has been built.



The demolition of the East Stand in late 2021. The lead contractor was Clelands Construction and many contractors were locally based.  



Work under way on the foundations of the new facility in March 2023.  



Some 400m3 of concrete was used in the construction of the foundations. 



Steel construction of the East Stand began in early 2023.  



The steel frame of the rear of the East Stand.   

 

 
The new stand starts to take shape in July 2024.  

 


An aerial shot showing the completed roof in December 2024. 

 


The needs of the venue’s sports users are accommodated under one roof with the completion of the East Stand.